Construction update: Pile-capping complete, deck slabs up next

Crews work near the future King County Water Taxi passenger ferry terminal in Seattle

When we last checked in on construction, crews were working to cap the 29 piles that will support our new passenger-only ferry facility on the south end of Colman Dock.

Last week, we hit a milestone when workers poured the last three pile caps, filling a portable hopper with concrete from a truck and then using a crane to position the hopper over the form. The caps were then cured under a plastic covering.

Crews work near the future King County Water Taxi passenger ferry terminal in Seattle

The next major step is installing deck slabs, which are being fabricated now and should begin arriving in about two months.

Crews are also building columns that will support the pedestrian bridge between our new facility and the Washington State Ferries terminal. They’re nearly finished tying the rebar for one of the two columns, and expect to start pouring concrete within the next two weeks.

Crews work near the future King County Water Taxi passenger ferry terminal in Seattle

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s